Permit cost is several separate charges collapsed into one word, and they behave differently. The building permit fee is rarely the largest. Impact fees usually are, and many jurisdictions waive them entirely below a defined square footage. This page separates the charges and shows where the threshold matters.
Nationally, ADU permit fees typically range from $3,000 to $12,000, covering plan checks, building permits, impact fees, and utility connections.
In California, under AB 68, local agencies cannot charge impact fees for ADUs under 750 square feet.
For California ADUs 750 square feet or larger, impact fees must be charged proportionally to the square footage of the primary dwelling.
California school districts can levy impact fees on ADUs larger than 500 square feet, per Education Code Section 17620.
A garage conversion permit in Los Angeles costs approximately $1,500, as it does not add new square footage or trigger impact fees.
Figures below are researched market numbers for budgeting and comparison. They are not quotes. Final pricing depends on your site, your jurisdiction, finish selections, foundation and utility distance.
ADU rules are set locally and change often. These are the provisions that most commonly control the outcome. Verify against your own jurisdiction before you design anything.
Permit cost is several separate charges that get collapsed into one word, and they behave differently. The building permit fee itself is usually calculated from construction valuation and is rarely the largest component. Plan check is a separate fee for reviewing your drawings. Impact fees are charges for the unit's incremental demand on infrastructure such as water, sewer, parks, transportation and schools, and they are frequently the largest single line.
The most useful thing to know is that several jurisdictions and some state statutes waive impact fees entirely for ADUs below a defined square footage. Where that applies, the marginal cost of crossing the threshold is not the construction cost of the extra square feet but the entire impact fee package that the waiver would have covered. That can make a slightly smaller unit substantially cheaper.
Also budget for the charges that are not permits but arrive at the same time: utility connection or capacity charges paid to the water and sewer provider, electrical service upgrade if your panel cannot carry the additional load, and any required third-party reports. Ask your building department for a written fee estimate for your specific project. Most will provide one, and it is far more reliable than any general figure, including the ones on this page.
| Building permit fee | Usually calculated from construction valuation. |
| Plan check fee | Separate charge for drawing review. |
| Impact fees | Often the largest line. Frequently waived below a size threshold. |
| School fees | Assessed per square foot in some states. |
| Utility capacity or connection charges | Paid to the utility, not the city. |
| Electrical service upgrade | If the existing panel cannot carry the load. |
| Third-party reports | Soils, survey, energy compliance. |
| Written fee estimate | Request one from your building department. Most will provide it. |
Most pages on this subject put the cost behind a contact form. The reasoning is understandable and the result is that you cannot budget, cannot compare, and cannot tell whether a bid is reasonable until you have already given up your phone number to three companies.
We publish the figures instead. They are researched market ranges rather than quotes, and site conditions will move them more than any other factor, but a range you can plan against beats a call-back you have to wait for. The constraints that decide feasibility — setbacks, height, utility distance, site access — are stated up front for the same reason. If your project is not viable, that is worth knowing on the first visit rather than the third phone call.
Factory production windows move with queue depth, material lead times and seasonal demand. We quote the current window rather than a fixed promise, because anyone promising a specific delivery date months out without seeing the factory schedule is guessing. Permitting is usually the longer pole: in ministerial states the review clock is defined by statute, while in discretionary jurisdictions it can run considerably longer.
The sequence that controls your schedule is site plan, permit submittal, plan check and corrections, permit issuance, factory slot, delivery and set, then utility connection and final inspection. Factory build time overlaps permitting only if you commit to the slot before permits are issued, which carries its own risk.